Imitation granite construction method
Release time: 2024-04-15 11:14
Rock paint is aimitationThe decorative effect of granite has a natural color, giving people an elegant, harmonious and solemn aesthetic feeling.
I. Construction Preparation
1.The distance between the foot lever and the wall is500-600mmThe wall has no support point.
2The grass-roots should be clean, no dust, rust, oil stains, no empty drum, pulverization, peeling, sand and other phenomena, the grass-roots surface should have a certain strength, moisture content
Note:In addition to the above supporting materials, cement, sand, construction glue, etc. Because of the need for local repair of the base.
II. Preparation of construction tools
Third, building protection
1Protection before construction:Finished products of doors and windows, iron and other components shall be protected before construction. The effective method is to wrap it with plastic cloth to prevent the pollution of building stone paint.
2Protection during construction:During construction, pay attention to the protection of windows, iron and other components, take reliable shielding measures during spraying construction, and pay attention to the protection of the upper wall after construction.
3Protection after construction:Sprayingimitation granite,Rock paint should be removed at any time. When removing the outer frame, take care to protect the outer wall. During the disassembly and transportation of the pipe rack, it is strictly prohibited to collide with the outer wall.
IV. Construction Process
1.Substrate Requirements:The wall surface shall be smooth and free of delamination, hollowing, surface cracks and obvious sand holes. If you exceed this limit, fill it with putty and sand it with sandpaper. Base alkalinityPHValue in10Below, the base layer is dry, and the moisture content is in10%The following.
2.usedimitation granite,The rock paint has a factory certificate and has been tested to meet the requirements of relevant national standards.
3.Usedimitation granite,Rock paint shall be approved by the Employer, the Supervisor and the Designer.
4.The scaffolding has been set up.
5.CONSTRUCTION CONDITIONS:The cuttings paint is a water-based paint, which requires high construction and maintenance conditions. Construction and maintenance requirements temperature higher5℃, the ambient humidity is lower85%to ensure good film formation. Low temperature will cause the paint film powder, cracking and other problems, environmental humidity will makeimitation graniteThe paint dries for a long time, which eventually leads to poor film formation. Constructionimitation graniteWeather must be considered when rock paint. Before applying rock paint,12Hours do not rain, to ensure that the grass-roots dry. After spraying24It does not rain for hours, so as not to damage the paint film by rain.